Who bears which share of the grid connection costs
Source: Section 118(4) EnWG (Energy Industry Act) in conjunction with Section 33(1) to (9) GasNZV (Gas Network Access Ordinance, version in force until 31 December 2025) · Bundesnetzagentur (Federal Network Agency), FAQ on biogas injection (as of 10 March 2026)
If biomethane is to be injected into the gas grid, the plant needs a grid connection. Under Section 118(4) EnWG (Energy Industry Act) in conjunction with Section 33(1) to (9) GasNZV (Gas Network Access Ordinance, version in force until 31 December 2025), the grid operator bears 75% of the grid connection costs. You, as the plant operator, are the connecting party: you pay the advance payment for the connection assessment and your share of the grid connection costs. Your share is capped at a maximum of €250,000 for a pipeline of up to 1 km.
This only applies if your advance payment for the connection assessment has been received by the grid operator by 31 December 2026. For this to work in time, CleanCycle needs your plant questionnaire by 30 November 2026. For this to work in time, submit your plant questionnaire to CleanCycle now.
What must be in place by when
- By 30 November 2026Submit nowPlant questionnaire to CleanCycleSimply leave blank any fields you are unsure about.So that your advance payment reaches the grid operator in time. Simply leave blank any fields you are unsure about.
- By 31 December 2026Your advance payment must have reached the grid operatorYou pay the advance payment for the connection assessment to the grid operator; it must have been received by then.
- ThenThe grid operator bears 75%of the grid connection costs. Your share as the connecting party: at most €250,000 for up to 1 km of pipeline.
Section 118(4) EnWG (Energy Industry Act) in conjunction with Section 33(1) to (9) GasNZV (Gas Network Access Ordinance, version in force until 31 December 2025)
The grid connection request – the application to the grid operator for a grid connection – does not yet commit you to building.
Which plants the deadline matters for
The deadline concerns the connection to the gas grid. Whether this is an option for your plant depends on one of the five questions CleanCycle uses to assess a plant: is there a gas pipeline nearby?
Where a grid injection point is nearby, the gas goes into the grid. For this, the raw biogas is brought to at least 97% methane by membrane upgrading.
If there is no gas grid nearby, there is the virtual pipeline: the biomethane is upgraded on site, compressed to 250–300 bar and taken by trailer to the hub or directly to the customer. Several plants in a region use a shared hub. Nothing changes on your farm.
Where the grid connection sits in the project
The plant questionnaire is the first of five steps. It is followed by the initial assessment, the site visit with the batch test, and the concept and offer with a letter of intent. The grid connection itself belongs to the fifth step: contract and conversion with grid connection, implementation and commissioning.
Every figure in the concept can be traced back to your plant’s substrate and process data.
We clarify details such as the advance payment, pipeline length and process for your plant in a conversation with you.
The starting point is the Post-EEG Check, free and without obligation, with five questions.