What changes when EEG support ends
In Germany, 9,605 biogas plants together generate 80.6 TWh of gross energy from biogas and biomethane – around one third of the volume generated in Europe.
Source: Fachverband Biogas e. V. (German Biogas Association), Branchenzahlen 2025 (industry figures 2025; as of 10 March 2026; number of plants estimated)
For a standard 500 kW plant, the electricity price falls by 25% after EEG support ends. The operating result (EBITDA) of this standard plant falls significantly.
Source: Electricity price after EEG support ends: Bundesnetzagentur (Federal Network Agency), average award values of the biomass tenders from October 2025 to October 2026 · Electricity price under the EEG and EBITDA: CleanCycle example 2026
According to a survey by the Fachverband Biogas (announcement of 15 January 2025), 76% of the plants surveyed would not be able to take part in tenders under the conditions prevailing at the time.
Source: Fachverband Biogas e. V., survey, announcement of 15 January 2025
Upgrade the gas, keep using the plant
CleanCycle is not a plant manufacturer. CleanCycle develops the project, finances the technology, builds and operates the optimisation itself and sells the gas together with the GHG quota. No new plants are built; existing infrastructure is upgraded: raw biogas from existing plants becomes biomethane and bio-CNG and goes to a market that is legally obliged to act – the GHG quota in transport.
Source: Section 37a BImSchG (Federal Immission Control Act – greenhouse gas reduction quota)
The product is primarily bio-CNG as HGV fuel. Where a grid injection point is nearby, the gas goes into the grid. If there is no gas grid nearby, the biomethane is upgraded on site, compressed to 250–300 bar and taken by trailer to the hub or directly to the customer. Nothing changes on your farm.
In addition, there is the biogas optimisation: FaserMAX is a mechanical substrate pre-treatment that breaks down grass, manure and maize fibres. This produces more raw biogas from the same substrate – around 20% more gas – verified in a batch test with your own substrates.
Sell your raw biogas, lease or sell your plant
- Sell your raw biogasYou continue to operate your plant and sell the raw biogas to CleanCycle. Payment is per kWh of methane in the raw biogas: a base price, and a higher price for high quality and volume. The offtake agreement runs for 15 years.
- Lease your plantCleanCycle takes over operation and conversion. You receive a fixed lease payment.
- Sell your plantThe clean exit with a purchase price. The acquisition takes the form of an asset deal or share deal based on capitalised earnings value, on request with a substrate supply agreement over 15 years.
Which option fits depends on whether you want to continue running your plant yourself, keep it but no longer operate it yourself, or exit. A non-binding sample calculation for a 500 kW plant can be found on the page Sell your raw biogas.
We clarify the details in a conversation with you: the criteria for “high quality and volume”, the amount and term of the lease payment and how the purchase price is determined.
Five questions: is your plant a fit?
- Does your EEG support end by 2032?
- Does your plant have 250 kW or more?Smaller plants are bundled with neighbouring plants.
- Is there a gas pipeline nearby?If not, the gas is transported by trailer.
- Do you use slurry or manure?This significantly improves the greenhouse gas value (GHG value) of your gas.
- Do you want to continue operating, lease or sell?
Source on the GHG value of slurry and manure: Directive (EU) 2018/2001 (RED II), Annex VI, Part A, biomethane for transport
From the plant questionnaire to the conversion
It starts with the plant questionnaire; simply leave blank any fields you are unsure about. This is followed by an initial assessment: which option fits. Next come the site visit and the batch test, in which the gas yield of your own substrates is measured in the laboratory. The concept and offer are drawn up on this basis; we then record the chosen option in a letter of intent. The final step is contract and conversion with grid connection, implementation and commissioning.
Every figure in the concept can be traced back to your plant’s substrate and process data.
- By 30 November 2026Submit nowPlant questionnaire to CleanCycleSimply leave blank any fields you are unsure about.So that your advance payment reaches the grid operator in time. Simply leave blank any fields you are unsure about.
- By 31 December 2026Your advance payment must have reached the grid operatorYou pay the advance payment for the connection assessment to the grid operator; it must have been received by then.
- ThenThe grid operator bears 75%of the grid connection costs. Your share as the connecting party: at most €250,000 for up to 1 km of pipeline.
The grid connection request does not oblige you to build.
Section 118(4) EnWG (Energy Industry Act) in conjunction with Section 33(1) to (9) GasNZV (Gas Network Access Ordinance, version in force until 31 December 2025)
More in the article Grid connection deadline: 75% covered by the grid operator.